| Product/Deliverable |
Due date |
| Perform complementary monitoring
and assessment of selenium and nutrient sources in the watershed |
12/20/2008 |
| Identify and assess selenium
BMPs/treatment technologies, including potential future
technologies |
3/31/2006 |
| Facilitate demonstration
testing of identified selenium treatment technologies and
BMPs |
3/31/2007 |
| Develop a draft selenium
offset, trading or mitigation program and submit to the
Regional Board Executive Officer for review |
6/20/2009 |
| Implement the final selenium
offset, trading or mitigation program upon approval |
12/20/2009 |
| Evaluate the nutrient TMDL,
including load/wasteload allocations and reduction targets
|
TBD |
| Develop a draft nutrient
offset, trading or mitigation program and submit to the
Regional Board Executive Officer for review |
6/20/2009 |
| Implement the final nutrient
offset, trading or mitigation program upon approval |
12/20/2009 |
| Develop a recommended selenium
site-specific objective for the Newport Bay/San Diego Creek
watershed if appropriate |
6/17/2009 |